Demand threshold for computing groups
ERCOT plans to activate limits for transmission providers and market schedulers once a group's combined simultaneous demand reaches roughly 2,500 megawatts. The assigned shares for the fourth quarter of 2026 total 2,720 megawatts. Because this step is conditional on demand reaching the threshold, it is a plan rather than a confirmed activation date.
In September, the northern group reached a simultaneous draw of 1,615 megawatts, although its sites had approval for 5,465 megawatts. That September figure is below the roughly 2,500 megawatt level at which ERCOT plans to activate limits.
Miner curtailment during Winter Storm Fern
During Winter Storm Fern in January 2026, cryptocurrency miners cut their demand by an estimated 4,100 megawatts. The estimate equals nearly 5% of the peak ERCOT had prepared to meet. The reduction was an estimate, not a metered total.
Status of Riot's Corsicana mine
Riot said its existing Corsicana operations qualify for an exemption from new requirements to stay connected through voltage and frequency disturbances. However, the mine belongs to a group that ERCOT monitors. The plan for that group had not been activated as of the filing, so the exemption and the group plan are separate matters.
Riot booked about $24.7 million in power credits across its markets in the third quarter. The credits came from power sales and demand-response programs. The figure is a third-quarter booking, not a cumulative total for other periods.
Lease terms at Corsicana
Riot's lease with Anthropic at Corsicana covers 910 megawatts of planned capacity, with the first block due in June 2027. Riot needs the tenant's consent to voluntarily cut supply. Orders from a utility or grid operator take precedence over that consent requirement.