Setting aside the accounting charges, Anthropic is also spending heavily to support its growth. The Telegraph reported that computing and infrastructure costs reached nearly $9 billion in the first half of 2026, already exceeding the company’s spending on those items for all of 2025.
Anthropic’s revenue climbed to about $16.3 billion in the first half of 2026, compared with $1.1 billion in the same period last year and total revenue of $4.6 billion for all of 2025.
The size of Anthropic’s compute bill
Anthropic has made a lot of commitments to ensure the computing capacity needed to expand its AI business is well and truly secured. The company’s cloud contracts all total about $450 billion over the next seven to 10 years, which is a figure that could rise to $750 billion as the company negotiates additional deals.
These commitments include about $111 billion for Google Cloud, $110 billion with Amazon Web Services and $31 billion with Microsoft.
Anthropic has also agreed to spend up to $86 billion renting Nvidia chips from Nscale and Lambda, along with more than $160 billion to lease Google chips through Broadcom.
A warning about data center opposition
According to Anthropic, the growing opposition to data center construction could pose a political risk, adding in its prospectus that resistance to new projects was becoming more and more organized across different jurisdictions.
Most of Anthropic’s data center capacity is based in the United States, although the company has signed letters of intent for facilities in other countries.